GIGASPUD View sitesSites
Floating AI compute · spud-barge nodes

Where a GigaSpud can plug in.

A spud barge pins itself to the seabed beside a stranded power switchyard, takes grid power through a subsea export cable, and cools a GigaEnergy AI pod with the water it floats on. This map is the site shortlist: how much power is on the fence line, how it reaches the barge, and what stands in the way.

Candidate sites

Click a marker or a row. Green and teal are the sites with a transmission-class yard and sheltered water; amber are showcase or pilot-scale sites; grey are secondary options kept for comparison.

Tier 1 — GW-class yard + harbour Tier 2 — fastest route to a real GW Tier 3 — sheltered NorCal water + 230/500 kV Tier 4 — SF Bay showcase (5–50 MW) Other — secondary / comparison
#SiteTierTie-inPower on siteWaterData

How to read the numbers. "Sourced" figures link to a published document. "Unverified" figures are from general industry knowledge and must be confirmed against CAISO / ERCOT interconnection data before any of this goes into a pitch. Coordinates marked ✓ come from Google Places; the rest are approximate to ~500 m and need a survey fix on the actual switchyard fence and berth face.

How grid power reaches the spud barge

The same chain offshore-wind substations use, run in reverse: transmission in, compute out. Every site on the map is scored on how many of these five links already exist.

1 · Shore switchyard230–500 kV

A retired or stranded plant's yard. The interconnection agreement is the long pole — reuse a retired generator's queue position where possible.

2 · Step-down→ 33–66 kV

Onshore transformer bank. 1 GW at 66 kV ≈ 9 kA, so three to four 630 mm² circuits, or one HVDC pair for longer runs.

3 · Export cablesubsea or quay-run

Buried or trenched to the berth. Budget $1–3M per km per circuit installed; most sites on this map need under 1 km.

4 · Dynamic section + hang-offtide · chop · barge motion

Flexible cable section into a hang-off on the spud barge, then 66 kV GIS switchgear on deck. Standard floating-substation hardware.

5 · GigaSpud deck→ 400–800 V DC racks

Transformers and rectifiers feed GigaEnergy pods. Seawater heat exchangers reject ~1 W of heat per 1 W of compute — the reason to float at all.

Scale per barge

≈ 300 MW

  • Roughly 150–200 containerised pods on a 120 m × 36 m deck barge
  • A GW is a flotilla of 3–4 spudded barges on one 66 kV ring, or one purpose-built hull
  • Spuds hold station in 10–40 ft water on mud or sand — SF Bay, the Delta and the Gulf all qualify
Cooling

Seawater is the product

  • Open-loop or titanium-plate heat exchangers; no cooling towers, no evaporative water use
  • Thermal-discharge permit (ΔT at the outfall) is the gating environmental approval
  • Cold Pacific water (SF Bay ~12–18 °C) beats Gulf water (~25–30 °C) for PUE
Alternatives to the grid

Powership or SMR alongside

  • Gas-turbine power vessels: ~470 MW per hull today; LNG bunkered by ship — the route the Texas projects are taking
  • Floating SMRs: 70–300 MW per unit, 2030s regulatory horizon
  • Both skip the interconnection queue; neither skips the air or nuclear permits

The GigaEnergy pod and the Giga family

One pod, three ways to move it. The pod is the compute and power unit; skid, sled and spud are how it gets to land, to the shoreline, and onto the water.

GigaEnergy pod

The unit

  • 40 ft high-cube container, liquid-cooled GPU racks
  • 1–2 MW IT load per pod; 400–800 V DC bus in, coolant loop out
  • Modular: a site is N pods, never a custom build
GigaSkid

Land · yard · truck

  • Steel skid frame the pod is built on — forklift, crane, flatbed
  • The pod's permanent chassis; sled and spud both carry a skid
GigaSled

Beach · mud · ramp

  • Drags the skid where wheels can't go — down a boat ramp, across a tideflat, onto a barge
  • Towed by dozer, tractor or winch
GigaSpud

On the water

  • Spud barge: steel legs drop through hull wells into the seabed and hold position without swinging
  • Tug moves it, spuds hold it, the export cable feeds it

Roadmap

Stage 0

Billboard barge · SF Bay

  • One spud barge, one pod shell, mesh-vinyl sign, battery-lit at night
  • Proves mooring, permits and visibility off the Embarcadero / Alameda
Stage 1

5–30 MW pilot · Oakland or Alameda Point

  • Port 12 kV or 115 kV feeder, 3–15 pods, seawater cooling loop
  • Same scale as the Stockton floating data centre that already runs in California
Stage 2

100–300 MW node · Moss Landing or Pittsburg

  • Reuse a retired generator's interconnection at a 230/500 kV yard
  • First full deck barge; one 66 kV export circuit
Stage 3

GW flotilla · Texas Gulf or Moss Landing

  • 3–4 barges on a 66 kV ring, or powership-fed where the queue is too slow
  • Only credible with a transmission interconnect or on-dock generation

Permits and gating items (California)

Electrical

  • CAISO interconnection (or ERCOT in Texas) — years, unless a retired unit's position is reused
  • PG&E / SCE wholesale distribution or transmission service agreement
  • CPUC review for any resource-adequacy or utility contract

Water and shoreline

  • BCDC permit for any moored structure in SF Bay; Coastal Commission outside the Bay
  • Regional Water Board NPDES permit for thermal discharge
  • US Army Corps Section 10 / 404 for spuds and cable in navigable water

Marine

  • USCG: lighting, anchor/moored-vessel signals, licensed tug operator
  • Stay clear of ship channels, ferry lanes and anchorages
  • ABS or BV approval-in-principle for the barge-as-data-centre, as the Texas projects obtained

Local

  • Port or city lease for the berth and shore landing
  • Community: Moss Landing's 2025 battery fire and West Oakland air-quality history both shape consent
  • Signage rules if the barge doubles as the billboard